Planned Maintenance: Samrand Data Centre UPS Maintenance

Notice ID: #3763
Start: 09 May 2019 18:00 SAST
Maintenance Window:8 hours
Point of impact:Samrand Data Centre
Issue:Routine maintenance
Attending: Hetzner Engineers
Additional Information:During the maintenance window one UPS unit will be placed into Bypass mode for routine maintenance. All power feeds will remain live for the duration of the maintenance window. In the event of a power failure, backup power will be provided by alternative UPS system and generator.