Emergency Maintenance: Samrand Data Centre UPS B2 Unit

Resolved Date:15 May 2019 22:50 SAST
Notice ID: #3792
Start: 15 May 2019 21:00 SAST
Maintenance Window:9 Hours
Point of impact:Johannesburg Data Centre
Issue:Emergency maintenance on UPS B2 Unit
Attending: Hetzner Engineers
Additional Information:During the maintenance window one UPS unit will be in service at a time for routine maintenance. All power feeds will remain live for the duration of the maintenance window.

In the event of a power failure, backup power will be provided by alternative UPS and the alternate generator supply. Colocation customer equipment that is connected to A or B supply will be protected by UPS supply.

No interruption to power is expected to any IT Equipment.